Client Case Study: Eileen from Mount Gravatt East

Eileen, a resident of Mount Gravatt East (4122), was experiencing a strong sewage smell in her home. Concerned about the potential health hazards and damage to her property, she decided to seek professional help.

Finding Us Through Brisbane Magnet

After searching for reliable plumbing services in her area, Eileen came across our ad on Brisbane Magnet. Impressed by our positive reviews and reputation as top-notch plumbers, she gave us a call.

Assigned Technician: Ethan

We quickly dispatched our experienced technician Ethan to attend to Eileen’s issue. With years of experience under his belt and extensive knowledge in sewer systems, we knew he was the best person for the job.

The Job Description & Solution

Ethan arrived at Eileen’s home and carried out an investigation on the source of the sewage smell. After thorough inspection, he found that there was a sewer overflow from a drain underneath the house. He gained approval for jet-blasting and CCTV inspection.

Despite several hours of continuous jet-blasting, Ethan could not successfully clear the blockage as it turned out to be collapsed pipework. He provided an onsite price for emergency spot dig repair which Eileen accepted after understanding the scope of works:

  • Lay down back plastic and set up equipment
  • Excavate in marked area down to collapsed section of pipework and expose
  • Cut out collapsed section area and restore flow to drain
  • CCTV inspect upstream and downstream sections for any further issues
  • Provide a further quote if needed
  • Supply and install new PVC pipework and fittings with directional risers
  • Test and commission works
  • Backfill with correct bedding

Further Works Required

Ethan returned to Eileen’s home to complete the CCTV inspection after the pipework was removed. He found that a large concrete boulder had crushed the pipework, causing the blockage. Upon further inspection, he also discovered three main root intrusion issues downstream.

Ethan provided Eileen with an onsite price for additional works which she accepted under the following scope:

  • Complete three x3 1 meter sectional re-lines as below:
  • – Use of high pressure jet-blast
    – Use of root cutting head
    – Measure length of re-line
    – Set up re-lining equipment onsite
    – Set up resin kit onsite
    – Wet out liner with resin

  • – Install resin into sewer service
  • – Use of compressor to inflate calibration hose